Increasing Capacity to 160000
This website has been designed with accessibility in mind. We are working towards having the content meet compliance of the Web Content Accessibility Guidelines 2.0 Level AA. Documents from external organizations may not be accessible. If these documents are required in an accessible format, please call 905-404-0888.
2019 Streamlined Environmental Assessment
The Regional Municipalities of Durham and York, the owners of the Durham York Energy Centre (DYEC), have commenced an Environmental Screening Process in accordance with the Waste Management Projects Regulation (Ontario Regulation 101/07) of the Environmental Assessment Act to amend the Environmental Compliance Approval for the DYEC.
The Proposed Undertaking: The Environmental Compliance Approval for the DYEC currently allows the facility to process up to a maximum of 140,000 tonnes per year of waste for disposal at the site. The Regions are proposing to increase this amount by 20,000 tonnes per year for a total of 160,000 tonnes. The facility is capable of processing 160,000 tonnes per year with its current equipment and is currently being underutilized despite demand for additional waste disposal capacity for residential waste within the Regions. If approved, the expanded tonnage will allow for greater usage of the existing facility, reducing the reliance on alternate waste disposal facilities outside the Regions' borders.
Project Updates
- Regions studying processing increase at Durham York Energy Centre, open house to be held December 12 in Bowmanville (December 2, 2019)
- Regions studying processing increase at Durham York Energy Centre, open house to be held October 23 (October 15, 2019)
- Regions studying capacity increase at Durham York Energy Centre, open house to be held August 21 (July 29, 2019)
- Notice of Commencement (July 3, 2019)
- Regions proposing to increase waste processing limit by 20,000 tonnes at Durham York Energy Centre (June 27, 2019)
Public Information Centres (PIC)
PIC #1 – August 21, 2019 |
PIC #2 – October 23, 2019 |
|
PIC #3 – December 12, 2019 |
DYEC Environmental Screening Report |